|
On the 17th
March, the Minister for Defence released his comments on the US
Government Accounting Office (GAO) Report on the JSF Project. As with
almost everything that comes out of Defence, the comments are important
not for what they say, but for what they don't say.
The Minister makes
much of the progress made in completion of the program re-baselining
and the flight of the first aircraft. No mention is made of that
aircraft not being representative of the production aircraft, so the
flight test data collected will have little value. More importantly,
the GAO's statement on this issue was ignored:
"…cost and
schedule goals established in the fiscal year 2004 rebaselined program
have not been met'" [Click for more
...]
The Minister then
goes on to say that analysis shows the JSF is meeting all performance
specifications except one, a statement presumably based on Contractor
and Program Office claims. The GAO Report is blunt on this issue
"Most ground
and flight tests will have to be completed before all the key
performance estimates are confirmed. At this time, the program has
completed less than 1 percent of the flight test program and no
structural durability tests have been started." (Pages 13 and 14)
On the subject of
the development of JSF production facilities, the Minister simply noted
that positive progress had been made, but the GAO Report gave a much
more realistic analysis, reflecting, not surprisingly, the many
complexities and risks inherent in such a program. For example:
“The Defense
Contract Management Agency has rated manufacturing as high risk,
stating that the primary cause of risk is the late delivery of parts to
properly support the manufacturing work flow. It projects further
delays to schedule, increased costs, and subsequent out-of –sequence
work." (Page 12)
“Design and
manufacturing of development aircraft has been a major source of
delay." (Page 10)
"Given that
only one aircraft has been built, and essentially all of the flight and
static and durability testing remains to be done, there is still
significant risk that the JSF design for each of the three variants
will incur more changes as more design knowledge is gained." (Page 13)
On the important
question of the benefits to likely be gained from some concurrency
between testing and production, the Minister's media release
misrepresents the GAO's position which is supported by several other
identified, responsible organisations. For example:
"These
oversight and testing organisations highlight some of the program risks
and the challenges the JSF program must overcome to avoid further slips
in schedule and more cost growth." (Page 20)
The Minister spent
some time on the question of costs. He recognised that there were a
number of increases, but seemed to wave them aside as being outside the
control of the JSF program. The GAO Report was again far more blunt
and revealing, see report pages 3, 6, 7, 8, 12, 16, 17, and 22. For
example:
"JSF program
cost estimates have increased by $31.6 billion since the program's
decision to re-baseline in fiscal year 2004. During this period,
estimates in some cost areas grew by $48 billion but were offset by
$16.4 billion due to quantity changes and the proposed termination of
an alternate engine program. According to the program, the cost
estimate is still mostly based on cost estimating relationships-like
cost per pound-not actual costs and, therefore, is subject to change as
the program captures the actual costs to manufacture the aircraft."
(Page 6)
"Even as the
JSF program enters the mid point of its development, it continues to
encounter significant cost overruns and schedule delay because the
program has continued to move forward into procurement before it has
knowledge that the aircraft's design and manufacturing processes are
stable." (Page 22-Conclusions)
With the wild
discrepancy between what the GAO actually reported and what Defence
says it
reported, one must conclude that the department still refuses to
acknowledge reality, and still seeks solace behind myths and
misconceptions.
In seeking a reason
for this, we have to go back to the original decision to take on an
aircraft far too early in its development - something the RAAF would
have avoided studiously from experience. The GAO Report should give
Defence a strong warning that an urgent re-evaluation of its flawed
position is imperative.
Finally, the tone
and tailoring of the Minister's media release, indeed everything now
coming from Defence, indicates a most unhealthy influence from its
Public And Corporate Communications, now 'Coordination Public Affairs',
watch dog. Let's have some straight talking directly from those
responsible for the proper management of Defence matters!
|